Brussels

Hydraulic sheet pile frame DPV 600, without vibrations and without soil settling.

DPV 600 Aufbau

Assembling the hydraulic sheet pile frame on the job site

 Anfang Aushub auf 4.500mm Tiefe

Start of excavation till 4.500 mm below ground level.

 Dielen auf Tiefe bringen

Pressing in the sheet piles with the hydraulic beam.

 Betonrohr verlegen

Bringin in the 800 mm concete sewerage.

 Kritische Stelle. Rohr verlegen neben altes Haus ohne Fundament.

Critical jobsite, installing sewerage next to an old house with shallow foundation.

 Rohr verlegen

Before all activities the house was extra secured.