Hydraulic sheet pile frame DPV 600, without vibrations and without soil settling.
Assembling the hydraulic sheet pile frame on the job site
Start of excavation till 4.500 mm below ground level.
Pressing in the sheet piles with the hydraulic beam.
Bringin in the 800 mm concete sewerage.
Critical jobsite, installing sewerage next to an old house with shallow foundation.
Before all activities the house was extra secured.